26/00053/FULL decided approve
Last updated 03/04/2026, 04:52
Application to install electrical infrastructure and related works for an electric vehicle charging hub.
Full Application
14, Mayflower Retail Park, Gardiners Link, Basildon, SS14 3HZ
SS14 3HZFull Proposal
Installation of electrical infrastructure and associated works to support an electric vehicle charging hub (EV Hub).
Application Timeline
- Application Registered
- 20/01/2026
- Application Validated
- 22/01/2026
- Target Decision Date
- 18/03/2026
- Committee Date
- N/A
- Decision Made
- 06/03/2026
- Decision Issued
- 06/03/2026
Case Officer
Applicant
GRIDSERVE Sustainable Energy